![]() |
|
|||||||||||||||||||||||
|
Windsor Terrace Auditor's Report 2007/010
|
||||||||||||||||||||||||
|
|
Complaint lodged on 6 November 2006, by Ms Astrid Vella on behalf of Flimkien G]all-Ambjent A]jar, concerning the approval of PA 6361/04: "To demolish existing dwelling and erect apartment block with semi-basement garage". An investigation was carried out in terms of Section 17C of the Development Planning Act. Facts Mr John Littlejohn submitted an outline application (PA 6361/04) on 8 November 2004 to demolish an existing dwelling and erect an apartment block with semi-basement garage. The proposed development was located at 75 Windsor Terrace, Sliema, within the Sliema UCA. On 2 December 2004, the Heritage Advisory Committee reviewed the application and recommended the following:
The Development Permit Application Report was inserted in the file on 6 January 2005 with a recommendation for refusal. The reasons for refusal were Structure Plan Policies UCO7, UCO 8, UCO 10, BEN 2, UCO 6, paragraph 11 of Part A of the Design Guidance: Development Control within Conservation Area, UCO 13. The reasons given can be summarised as follows:
The DCC Division 'C' refused the application on 7 March 2005. The applicant applied for his application to be reconsidered on 4 April 2005. The Planning Directorate re-assessed the application and reiterated its previous recommendation for refusal of the application. On 19 December 2005, the DCC reviewed the application and decided to defer a decision in order to carry out a site inspection. At the same time it stated:
The DCC inspected the site on 18 January 2006 and minuted the following:
The DCC approved the application on 18 July 2006 on the basis of amended plans which retained the existing façade in part with the following justification:
It is to be noted that the MEPA Board approved the North Harbour (this includes Sliema) Local Plan on the 2 May 2006. This came into force on 3 August 2006, following its approval by the Hon. Minister. According to Map SJ3 of the relative Local Plan, the area where this development is located is zoned for two floors. Comments The Development Permit Application Report: The case officer considered the application on the basis of current policies concerning UCA's. Whilst a number of similar applications in the same locality were considered, I find it difficult to understand why the case officer did not attach to his report a block plan indicating existing heights. This would have been particularly useful in Sliema, knowing too well the number of conflicting decisions taken on the demolition of buildings and their replacement with buildings much higher than the original. There seem to be a reluctance from case officers to use graphics to better explain their statements. This is difficult to explain as most MEPA staff are trained in graphical communication. Such a document would have explained clearly the situation without the need of lengthy descriptions. The actions of the DCC These are very difficult to explain. At the first instance the DCC accepted the recommendations of the Planning Directorate and refused the application listing seven reasons, based on official polices as to why the development was unacceptable. Subsequently, at reconsideration stage, the members of the DCC changed their minds and reversed the previous decision. The reasons given, in no way address or contradict the original reasons for refusal - indeed, the reasons purporting to justify the overturning of the original decision are quite irrelevant.
The DCC knew well enough that the Local Plan for the area was due to be published shortly (within days!). Yet they did not take the precaution to consult the finalised Local Plan so that by their action they will not compromise its provisions. This is required by the Structure Plan Policy BEN 4 which states that
The Local Plan: As
stated above, the Local Plan for the area determines the height limitation
on this site of two floors. Obviously this policy was adopted to retain
the existing houses in their context. However, the MEPA is now committed
with the applicant to issue a permit for a building with six floors, and
this commitment can have very serious implications. It is to be noted
that the permit was sent to the applicant on 18 October 2006, over two
months after the approval of the Local Plan (although it was approved
on the 18 July 2006). It is not clear what led to this excessive delay. Conclusion and recommendations In view of the above, it is concluded that:
2. There are no grounds for the withdrawal or modification to the permit in terms of Section 39A of the Development Planning Act as none of the reasons justifying withdrawal or modification established in the said Section 39A exist. In addition the Development Planning Act does not stipulate any alternative action to modify or withdraw a permit when the policies were not properly applied.
I issued a Preliminary Report on the 16 November 2006 and subsequently on the 11 December 2006 I met the Chairman MEPA and his legal advisor. It was pointed out to me that in terms of Section 33 of the Development Planning Act, the Outline Development Planning Permit supercedes the provisions of the applicable Local Plan (approved in August 2006). In view of the outcome of this meeting, I have amended the Preliminary Report as originally drafted. Joseph Falzon |
|||||||||||||||||||||||
|
|
||||||||||||||||||||||||